EllisDon, the acting Construction Management representative for Gateway Casinos, has contracted DFI for their project in Delta, BC.  Here are the details:

  • Piles are to support a new casino development at the Junction of Highway 99 and Highway 17A in Delta, BC. (https://gatewaycasinosdelta.com/)
  • The scope of work includes: assisting with the helical pile design, pile fabrication and shipment, survey services, and installation of piles and pile caps.
  • 1141 helical piles.
  • The piles are 324mm X 18.288m (12.7mm wall thickness), with two 31.8mm thick X 762mm diameter helixes.
  • Over 88 loads of freight.
  • Two track cranes required for installation. The ability to install piles in a single length provides a significant cost savings for the client.
  • Challenging geotechnical conditions, including the water table at 1 metre below grade and seismic considerations including a liquefaction zone from 1 to 15 metres below grade.
  • This large project is adjacent to a major thoroughfare with roughly three million vehicles in road traffic per year.
  • Project is expected to take roughly 55 days to complete.

23

Oct

We’re proud to showcase one of our most recent piling ventures for an ammonia storage facility in Deer Park...

30

Sep

EllisDon, the acting Construction Management representative for Gateway Casinos, has contracted DFI for their project in Delta, BC.